100618-01R4-5/08As an ENERGY STAR® Partner, Burnham Hydronicshas determined that theMST288, MST396
10A. CAST IRON SECTION ASSEMBLY TAPPINGS Refer to Table 3 "Purpose of Tappings and Bosses" and Figure 7. 1. All tappings have factory ins
11Figure 4: Boiler Removal from Skid
12Figure 5A: Partial Front View - Burner Swing Door Mounted to Boiler - Fully Closed and Secured1. To open/remove Burner Swing Door (mounted on Cast
13Figure 5B: Top View - Burner Swing Door Mounted to Cast Iron Block Assembly (Jacket Removed for Clarity) By design, door insulation on model MST62
14 E. FLUEWAY BAFFLE INSTALLATION. Flueway bafes are enclosed into Part Carton. Bafe requirements differ by boiler model, see Table 2.TABLE 2:
15Figure 6: Flueway Bafe Positioning/Orientation in FluewaysNOTICEWhen securing burner swing door make sure door is drawn-in equally on both sides.d
16Figure 7: Purpose of Tappings and BossesTABLE 3: PURPOSE OF TAPPINGS & BOSSESTapping LocationSize, NPT Boss LocationThread Size UNCSteam Boile
176. Repeat above steps with right Cleanout Cover.7. Apply the adhesive sealant to the underside of the collar, all around, at the inside corner of
18L. TRIM AND CONTROLS INSTALLATION. Pressure Limit Installation.1. Locate and remove L404F Pressure Limit with factory attached harness from C
19Figure 9: Float-Type LWCO and Pressure Limit Installation
2IMPORTANT INFORMATION - READ CAREFULLY The following terms are used throughout this manual to bring attention to the presence of hazards of vario
207. Screw LWCO to External Wiring Enclosure wiring harness (end with fork and female disconnect terminals) connector into low water cut-off J-box to
21Figure 10: Oil Burner Installationf. Insert oil burner into the opening of burner swing door. Align and engage keyhole slot in burner ange over
22 A. EVALUATE THE EXISTING STEAM SYSTEM. The single most important factor in determining the expected life cycle of a steam boiler, is the amou
23Figure 11: Recommended Boiler Piping for Gravity Return Steam Boiler
24SECTION IV: TANKLESS & INDIRECT WATER HEATER PIPINGA. CONNECT TANKLESS HEATER PIPING as shown in Figure 12. See Table 4 for Tankl
25TABLE 4: TANKLESS HEATER DATA: Figure 12: Schematic Tankless Water Heater PipingBoiler Model Heater No.Heater Rating (GPM)Pressure Drop thru Heate
26Figure 13: Alliance™ Water Heater Piping with MegaSteam™ BoilerB. CONNECT ALLIANCE™ INDIRECT WATER HEATER PIPING as shown in Figure 13.1. Ref
27A. Chimney Venting 1. Chimney venting is an important part of a safe and efcient oil red appliance system. Contact your local re and building
28Figure 14: Recommended Vent Pipe Arrangement and Chimney RequirementsFigure 15: Proper and Improper Locations of Draft Regulator
292. Type B Chimney Connector - a type B chimney connector can be used to transmit the ue gases provided ue gas temperature entering the chimney co
3DANGERDO NOT store or use gasoline or other ammable vapors or liquids in the vicinity of this or any other appliance. WARNINGImp
30Figure 17: Optional Air Intake Piping Installation - Only Available with Beckett BurnerWARNINGRemove the bafes if there are any signs of condensat
31c. Mount the vacuum relief valve into the tee and fasten with a screw and nut in collar tabs. To ensure proper operation, the gate must be level a
32A. GENERAL1. Install wiring and electrically ground boiler in accordance with requirements of the authority having jurisdiction, or in absence of
33Figure 18: Wiring Diagram, Steam, Hydrolevel CG450 Probe LWCO
34Figure 19: Wiring Diagram, Steam, McDonnell & Miller PS-801 Probe LWCO
35Figure 20: Wiring Diagram, Steam, McDonnell & Miller #67 Float LWCO
36BOILER SEQUENCE OF OPERATION WITH PROBE LWCO (See Figure 18)When the thermostat calls for heat, it energizes the R8285C Control Center relay w
37Figure 21: Single Pipe Oil LineSECTION VII: OIL PIPINGA. GENERAL1. Use exible oil line(s) so the burner swing door can be opened without dis
38TABLE 5: TWO-STAGE UNITS (3450 RPM) - TWO PIPE SYSTEMSTABLE 6: SINGLE-STAGE UNITS (3450 RPM) - TWO PIPE SYST
39SECTION VIII: SYSTEM START-UP1. SET ROOM THERMOSTAT about 10° above room temperature.2. PRESS RED RESET BUTTON on front of burner cover,
4WARNINGThis boiler contains very hot water under high pressure. Do not unscrew any pipe ttings nor attempt to disconnect any components of this boi
405. Adjust oil pressure.a. When checking a fuel unit's operating pressure, a reliable pressure gauge may be installed in either the bleeder po
41Figure 24: "L1" and "V1" Head Electrode Positioning and Gun Setting (Beckett AFG)
42WARNINGBefore installation of the boiler is considered complete, the operation of all boiler controls must be checked, particularly the primar
43 • Place a jumper across cad cell terminals. • Follow procedure to turn on burner. Burner must not start, indicator light turns on and co
44Important Product Safety InformationRefractory Ceramic Fiber ProductWarning:The Repair Parts list designates parts that contain refractory ceramic f
45SECTION IX: MAINTENANCE AND SERVICE INSTRUCTIONSA. MAINTENANCE OF LOW WATER CUT-OFF DEVICESWARNINGProbe and oat type low water cu
46 Operate the boiler with steam in the entire system for a few days allowing the condensate to return to the boiler. If the condensate can temporari
47by drawing a small sample of boiler water and testing with hydrion paper which is used in the same manner as litmus paper, except it gives specic r
48SECTION X: BOILER CLEANINGA. CLEAN THE FLUEWAYS (See Figure 27).1. For access to the combustion chamber remove the two (2) 3/8" - 16 cap
49Figure 27: Cleaning Boiler Flueways and Combustion Chamber SurfacesWARNINGThe boiler must be connected to an approved chimney in good condition. Se
5Figure 1: MST288 Thru MST629 Steam Boiler with and without Tankless Heater
50A. COMBUSTION1. NOZZLES — Although the nozzle is a relatively inexpensive device, its function is critical to the successful operation of the oil
51d. Excessive airow or draft causing ame to leave burner head.e. Excessive back pressure causing ame to be erratic.3. Control locks out after T
52Bare Boiler Assembly
53Item No.Description Part No. MST288 MST396 MST513 MST6291. BARE BOILER ASSEMBLY1A Front Section, Machined 100569-01 1 1 1 11B Center Section, Machi
54Bare Boiler Assembly
55Item No.Description Part No. MST288 MST396 MST513 MST6291. BARE BOILER ASSEMBLY (Continued)1SBurner Swing Door Insulation (Less Pockets) 100039-01
56Jacket Assembly
57Item No.Description Part No. MST288 MST396 MST513 MST6292. JACKET ASSEMBLY2A Jacket Front Panel Assembly w/Insulation 100575-01 1 1 1 12B Power Out
58MST288 Thru MST629 Steam Boilers - Trim and Controls
59Item No.Description Part No. MST288 MST396 MST513 MST6293. MST - TRIM AND CONTROLS3A6" RC-STD Draft Regulator 8116288 1 1 1 ---7" RC-STD
6TABLE 1A: DIMENSIONAL DATA (SEE FIGURE 1)TABLE 1B: RATING DATABoiler Model No.Dimensions (See Figure 1)Water Content (To Normal Water Line) - Gall
60Beckett AFG Burner
61BECKETT OIL BURNER PART NOS. FOR MEGASTEAM™ SERIES BOILERSNOTE: When ordering parts always give the serial and model numbers shown on the boiler an
62TABLE 8: BECKETT AFG BURNER SPECIFICATIONSBoiler ModelBurner Input (gph)Head Type (setting)Air Shutter (setting)Air Band (setting) NozzlePump Press
63SERVICE RECORDDATE SERVICE PERFORMED
By this Warranty Statement the U.S. Boiler™ Company, Inc. of Lancaster,Pennsylvania issues limited warranties subject to the terms and conditionsstate
7Figure 2: Minimum Installation Clearances To Combustible Materials (Inches)A. INSPECT SHIPMENT carefully for any signs of damage.1. All equipment
8NOTICEClearance to venting is for single wall vent pipe. If Type L vent is used, clearance may be reduced to the minimum required by the
9SECTION II: UNIT-PAK BOILER ASSEMBLYMegaSteam™ Unit-Pak Boiler Assembly ShipmentContent Check List (see Figure 3)1. ___ Cast Iron Section/Burner
Komentarze do niniejszej Instrukcji